Upgrade of Existing UF System for Water Utilities in Selangor

REMOX UF System Upgrade Water Utilities Selangor, ISME Malaysia

Refurbish and reprogram the existing UF control system to improve serviceability. Original system involves a singular PLC to control entire plant of 3 UF trains. Newly supplied system will control each UF train with its own PLC with the help of a master PLC.

Solutions

  • Existing main PLC program is split into individual train PLC program so that each train can be shutdown without affecting the other trains.
  • Main PLC and Sub PLC are designed to communicate with each other using OMRON FINS communication network for highest reliability.
  • The main Proface HMI is reprogrammed to accommodate new PLC structure and internal address.
  • Once all hardware is prepared, the system is swapped with the new hardware with minimum downtime to the plant.
  • A SCADA system is also installed in place to allow real-time data monitoring and data logging for future analysis.